Significant increase in availability
Based on several audits, Wärtsilä delivered a comprehensive solution to bring EDG’s power plant up to standard again; including a complete overhaul of engines and alternators. In addition, automation was upgraded and auxiliaries were modified and fine-tuned to suit the plant performance. Finally, the turbochargers were also upgraded with newer versions.
Thanks to the overhaul, all three engines now produce 10.4MW of electricity, which is a significant boost in EDG’s power requirement and grid stability. Mr Diaby says that EDG also took advantage of Wärtsilä’s service to have advisors on site after the commissioning. “For one year our personnel has gained valuable competence with the help of the two advisors from Wärtsilä. This training will benefit EDG in the future operation and maintenance of the plant.”
As a continuation to the project, Wärtsilä will also provide EDG with maintenance services and OEM spare parts for regular engine maintenance.
“The benefits of this project are many, but to mention the most important ones, we can now run the plant at full capacity and enjoy an increased availability rate of between 96% and 98%. With this said, we can recommend other power plant owners with similar needs to contact Wärtsilä. We had total satisfaction with this project,” says Mr Diaby.