Ensuring a more sustainable and reliable electric grid
Energy storage has become increasingly important to stabilise California’s electric grid, so much so that the California Public Utilities Commission (CPUC) approved plans in 2022 to add 15GW of new energy storage & demand resources by 2032.
With the integration of Wärtsilä’s energy storage system in Calexico, REV Renewables will provide resource adequacy obligations for utilities in the region and support various ancillary efforts for the California Independent System Operator (CAISO). The facility will reduce congestion on transmission lines moving between California and Mexico, enabling regional energy providers to add more flexible energy generation.
Who | REV Renewables |
What | 125 MW / 250 MWh |
Where | Calexico, California, USA |
MW of energy storage capacity
MWh of energy storage capacity
Battery energy storage is a key component to maintaining reliability and stability of California’s electricity grid. Wärtsilä worked with us to manage supply chain challenges, to collaborate with local communities and to perform site safety and training to bring this complex energy storage project online.
Customer | REV Renewables |
Site size | 125 MW / 250 MWh |
Site location | Calexico, California, USA |
Application(s) | Storage+ |
Scope of services | Engineering, Procurement and Construction (EPC), Service+ |
Delivery | 2022 |
Read the case study to get all the project details.