Wärtsilä signs service agreement for Mozambique power plant

Wärtsilä Corporation, Press release 29 April 2013 at 15:00 UTC+2

Wärtsilä, a leading global supplier of flexible and efficient power plant solutions and services, has signed an Operations & Maintenance (O&M) agreement with Central Termica de Ressano Garcia, owned by Sasol New Energy from South Africa and the Mozambique state utility, Electricidade de Moçambique (EDM). The three year agreement was signed in April 2013 and covers the company’s gas engine power plant in Ressano Garcia, Mozambique.

The Central Termica de Ressano Garcia plant will be powered by a total of 18 Wärtsilä 34SG engines running on natural gas, with the gas being fed from the Pande and Temane gas fields. It will be the largest power plant running exclusively on gas engines to be installed in Mozambique, and the second largest on the entire African continent. The power plant is scheduled for completion by May 2014, and the electricity produced will be sold to EDM.

“Our extensive experience and deep know-how in the O&M field, in combination with the efficiency and reliability of the Wärtsilä equipment, will be of great value in ensuring the success of this important project. The Central Termica de Ressano Garcia gas engine power plant is designed with high operating efficiency, low generating costs, and a minimal carbon footprint in mind. These are all areas where Wärtsilä excels. Wärtsilä’s presence in southern Africa is becoming increasingly significant, and is likely to strengthen further as the use of natural gas fuel continues to be developed,” says A.P.Singh, General Manager, Wärtsilä Solutions Support Services, South Europe & Africa.

By taking responsibility for operating and maintaining this power plant, Wärtsilä will implement its global best practices to ensure that it delivers the design output with maximum efficiency and minimal environmental impact. Local employees of Central Termica de Ressano Garcia will also be trained as part of this agreement.

Once completed, the power plant will significantly contribute to Mozambique’s power generating infrastructure, and will help meet the country’s growing demand for electricity. Furthermore, because of its low emissions this project will be a major advance in developing low carbon electricity generation in the region.

Wärtsilä is an experienced operator, with a proven track record in operation and maintenance services. Globally, more than 17 GW of generating capacity in both marine and land based installations – a total of 544 installations – is covered by Wärtsilä’s asset management and other service agreements. 28 such agreements are in Africa.The Central Termica de Ressano Garcia agreement is Wärtsilä’s first O&M agreement in the Republic of Mozambique.

An Operations and Maintenance agreement is a comprehensive form of asset management. Typically, O&M agreements can be tailored to cover the entire scope of operational, management, and maintenance services, as well as providing performance guarantees for the installation. Wärtsilä undertakes all aspects of operating and maintaining the power plant, including labour, spare parts, maintenance, administration, human resource services, the training of local employees, technical support, logistics management and security.

Image of the power plant

Wärtsilä press release 13 December 2012:
Wärtsilä to supply major power plant to Mozambique - biggest gas fuelled plant ever to be installed in the country

Read more about Wärtsilä Services

For further information please contact:

A.P.Singh
General Manager, Wärtsilä Solutions Support Services, South Europe & Africa.
Tel. +358 10 709 2603
a.p.singh@wartsila.com

Tuula Franck
Senior Manager, Media and Stakeholder Relations
Wärtsilä Corporation
Tel: +358 400 267555
tuula.franck@wartsila.com

Wärtsilä in brief
Wärtsilä is a global leader in complete lifecycle power solutions for the marine and energy markets. By emphasising technological innovation and total efficiency, Wärtsilä maximises the environmental and economic performance of the vessels and power plants of its customers.
In 2012, Wärtsilä’s net sales totalled EUR 4.7 billion with approximately 18,900 employees. The company has operations in nearly 170 locations in 70 countries around the world. Wärtsilä is listed on the NASDAQ OMX Helsinki, Finland.