• Media
    MEDIA

    at Wärtsilä in Singapore

Wärtsilä to add 128 MW of flexible baseload power to enable Indonesian mine expansion

Wärtsilä Corporation, Press release 21 October 2020 at 10:00 UTC+2
  • The fast-starting flexibility of Wärtsilä 34DF generating sets in the 128 MW power plant of an Indonesian mine enables the integration of energy from renewable sources in the future.  © Wärtsilä

The technology group Wärtsilä has received contracts for a 128 MW power plant in Indonesia. The plant has been ordered by PT Freeport Indonesia, one of the world’s leading mining companies. The extended engineered equipment delivery order comprises fourteen Wärtsilä 34DF dual-fuel generating sets. The order for eight generating sets was placed in June 2020, and a further six generating sets were ordered in September. A consortium consisting of Wärtsilä and PT PP will install, construct and commission the power plant.

The plant will be located at Amamapare, PT Freeport Indonesia’s port site in Papua, Indonesia. From here the electricity will be fed to the Grasberg mine via a 100 kilometres long transmission line. The mine is located in the remote highlands of the Sudirman Mountain Range in the province of Papua, western half of the island of New Guinea. Neither the mine nor the port site are connected to the 50 Hz grid. The mine operates on a 60 Hz power supply. The new plant is needed to provide the necessary power as the customer extends operations from open pit to underground mining of one of the world’s largest copper and gold deposits.

“We have completed open pit mining at the Grasberg minerals district, and are now developing large-scale, high-grade underground mines. For this it is critical that we have a reliable and efficient energy supply, and the Wärtsilä generating sets will deliver the power we need,” commented George Baninni, Executive Vice President, P.T Freeport Indonesia.

“The competitive total lifecycle cost of the Wärtsilä solution was ultimately the deciding factor in the award of this valuable contract. However, we have power plants operating in the vicinity of this site, which provided important references as part of the decision process. Our local presence in Indonesia is strong, with 5,3 GW of installed base and 350 employees on the spot. We are able to provide a high level of support,” said Kari Punnonen, Energy Business Director, Australasia, Wärtsilä.

The Wärtsilä 34DF engines can operate on a variety of fuels. This flexibility will allow the plant to switch to operating on natural gas when it becomes locally available. Initially the engines will run on Indonesian B30 biodiesel. The fast-starting flexibility of the engines will also enable the integration of energy from renewable sources, such as solar and wind, in the future.

The Wärtsilä equipment is scheduled for delivery between July and November 2021. The first seven engines are expected to be officially handed over in March 2022, with the remaining seven to be handed over in July 2022.

Read more:

Wärtsilä 34DF multi-fuel power plants
Wärtsilä solutions for mining and cement industries

 

Media contact for more information on this release:

Mirja-Maija Santala
Manager, Marketing & Communications
Wärtsilä Energy
Mob: +358 400 793 827

mirja-maija.santala@wartsila.com

Image caption: The fast-starting flexibility of Wärtsilä 34DF generating sets in the 128 MW power plant of an Indonesian mine enables the integration of energy from renewable sources in the future. 
© Wärtsilä Corporation

All Wärtsilä releases are available at https://www.wartsila.com/media/news-releases and at http://news.cision.com/wartsila-corporation where also the images can be downloaded.

Wärtsilä Energy in brief
Wärtsilä Energy leads the transition towards a 100% renewable energy future. We help our customers unlock the value of the energy transition by optimising their energy systems and future-proofing their assets. Our offering comprises flexible power plants, energy management systems, and storage, as well as lifecycle services that ensure increased efficiency and guaranteed performance. Wärtsilä has delivered 72 GW of power plant capacity in 180 countries around the world.
https://www.wartsila.com/energy

Wärtsilä in brief:
Wärtsilä is a global leader in smart technologies and complete lifecycle solutions for the marine and energy markets. By emphasising sustainable innovation, total efficiency and data analytics, Wärtsilä maximises the environmental and economic performance of the vessels and power plants of its customers. In 2019, Wärtsilä’s net sales totalled EUR 5.2 billion with approximately 19,000 employees. The company has operations in over 200 locations in more than 80 countries around the world. Wärtsilä is listed on Nasdaq Helsinki.